Same trades. Same site. Weeks faster.
Takt planning runs your trades like a train timetable — a steady rhythm of crews flowing zone to zone, instead of stacking and waiting. Put your phase in below and see exactly how much time (and money) a better plan releases.
Takt Inputs
✏️ Name your trades — make this your plan
Optional. Names appear when you hover the diagrams and in your PDF report.
Area & Cost Inputs
The Payoff
The Usual Way vs The Takt Way
The same phase, planned the way most projects plan it: trades pushed into zones before the crew ahead is finished. Red outlines mark crews stacked on top of each other — slower work, constant firefighting, no rhythm.
Compare it with your takt plans below: the same trades, the same scope — but every crew always has a free zone, and the whole site moves to one beat.
Your Best Options
We scored every zoning option against speed, flow quality, wasted trade time and your zone-size limits. Here are the three worth looking at — click one to load it into the plan below.
Show every option (the full engineering table)
All 36 zoning options. Click a row to draw it as the “Selected Plan”. The dark cell marks the option matching your current zone count. Hover any column heading for a plain-English definition.
| Pick | Takt Wagons | Takt Zones | Takt Time Unrounded | Theoretical Low Limit | Train Length | Takt Time | Duration | Trade Time Gained | Area per Zone | Takt Level | Realized Flow Potential | Efficiency Parametric | Value Parametric |
|---|
Shortest possible durations by takt time
For each takt rhythm, the highest zone count that still covers the work — and the resulting duration. This is the speed limit of your phase.
| Takt Time | Best # Zones | Duration |
|---|
Takt Plan — Current Inputs
Takt Plan — Selected Plan
Each colour is one trade crew flowing through the zones. Rows are zones, columns are working days. Press play and watch the train move.
Take Your Plan With You
This is one phase of one project. Imagine every phase of your programme flowing like this — trades that never wait, handovers you can set your watch by, and finish dates you can defend. That's what we build with our clients.